IMPORTANT NOTICE 1:
All required documents at the end of the semester:
1- A Project Planning & Management Report (PPM report should be sent as Word file and directly attached to your mail)
2- Progress Report Meeting Forms Signed by your Supervisor (At Least 4, At Most 8, Scan and Attach them to the Appendix of your Final Report before sending us)
3- A Final Report (should be sent as Word file and directly attached to your mail)
4- SourceCodes_Docs.rar file (IF YOU HAVE ANY of the produced documents, source codes, DB schemas, other outputs of your project, etc.)
NOTE: The "SourceCodes_Docs.rar" file should include the source codes, database, and other project outputs. If the .rar file is too large to be sent via email, please provide a cloud link specifically ONLY for this file. The shared cloud link should, if possible, allow unlimited access and be downloadable by anyone who clicks the link.
IMPORTANT NOTICE 2:
Files listed above (1,2,3) must be sent to: gurcu.oz@emu.edu.tr; duygu.celik@emu.edu.tr; mahmut.sevince@emu.edu.tr; YOUR PROJECT SUPERVISOR mail
IMPORTANT NOTICE 3:
In the PPM REPORT, the following items must be done:
| MAIN HEADINGS | CMSE / CMPE / BLGM |
1 | Are Preliminary Project Information tables filled? | All | |
2 | Is the Student Group table given or not? | All | |
3 | Is the Introduction To Project (summary of project, key words, aim of project, innovative aspects/contributions of project, methods to be applied, economic and national outcomes etc.) part written properly? | All | |
4 | Is there sufficient explanation on the Software Process Life Cycle Model? | All | |
5 | Are PERT or CPM techniques used to estimate the project duration? Are these shown in the Network Diagram model? | All | |
6 | Is Functional-Point Analysis applied to estimate the Line-Of-Code analysis of the planned project? | All | |
7 | Is COCOMO or another estimation technique used to estimate project budget or man-months required? | All | |
8 | Is any technique(s) used to reduce the project time duration (eg. Fast Tracking or Crashing)? | CMSE | |
9 | Are List of Work Packages discussed with details in tables separately? | All | |
10 | Is a Gantt chart created by using a project management tool (eg. MS Project, IBM Rational Pro, etc.)? | All | |
11 | Are the List of Milestones (should be matched with the Gantt chart) and start & finish dates given in a table? | All | |
12 | Are List of Risks and B Plans discussed in a table? | All | |
13 | Is the Project Team List given and responsibilities of team members are discussed in a table? | All | |
14 | Is the Organization Scheme illustrated? | All | |
15 | Is the Instrument / Equipment / Software purchase table given? | All | |
16 | PM tools are used?
| All | |
IMPORTANT NOTICE 5:
In the FINAL REPORT,
ABSTRACT
Table of Contents
LIST OF FIGURES
LIST OF TABLES
1. INTRODUCTION
2. PROJECT PLANNING AND MANAGEMENT
3. REQUIREMENTS ANALYSIS
3.1 Functional Requirements
3.2 Non-Functional Requirements
3.3 Realistic constraints
3.4 Ethical issues
4. DESIGN
4.1 High-level design (architectural)
4.2 Software design (USER INTERFACES, UML DESIGNS, DATABASE DESIGNS, ETC.)